RFNBO stands for renewable fuels of non-biological origin. In practice it means hydrogen made by electrolysis with renewable electricity, and the fuels derived from it: ammonia, methanol and synthetic fuels. The term is legal, not technical. Whether hydrogen holds RFNBO status decides whether it counts towards the European Union's binding targets, whether it can bid in European Hydrogen Bank auctions, and whether a buyer in the EU will pay a premium for it.

That is why the first question in this industry is "is it RFNBO", and only the second is "what does it cost". This guide explains what the rules require, where projects trip up, and what it all means for a producer outside the EU, including Serbia and the Western Balkans.

Where the term comes from

The basis is the Renewable Energy Directive. Its third version, RED III (Directive (EU) 2023/2413), has been in force since November 2023, and Member States were due to transpose it by May 2025. The directive sets the targets; two Commission delegated acts from 2023 set out how to prove that hydrogen is in fact renewable:

  • Delegated Regulation (EU) 2023/1184 defines when the electricity used in an electrolyser counts as fully renewable. These are the rules on additionality and on temporal and geographic correlation.
  • Delegated Regulation (EU) 2023/1185 defines how greenhouse gas emissions are calculated over the fuel's whole life cycle.

First condition: at least 70 per cent emission savings

The fuel must emit at least 70 per cent less than the fossil fuel it is compared with. The comparator is 94 grams of CO2 equivalent per megajoule, so the ceiling is 28.2 grams per megajoule. For hydrogen that works out at roughly 3.4 kilograms of CO2 equivalent per kilogram of hydrogen, counting production, processing and transport to the user.

The same 70 per cent threshold applies to low-carbon hydrogen, for example hydrogen from natural gas with carbon capture or from nuclear electricity. The Commission adopted the methodology for it in July 2025. Such hydrogen is not RFNBO, however, and does not count towards the targets described below.

Second condition: the electricity must be demonstrably renewable

This is where most misunderstandings arise. Regulation 2023/1184 provides several ways to prove the renewable origin of electricity.

Direct connection. The electrolyser is connected by a direct line to a renewable power plant, or sits in the same installation. The plant must not have come into operation more than 36 months before the electrolyser.

A grid with a very high renewable share. If the renewable share in the bidding zone exceeded 90 per cent in the previous year, grid electricity counts as renewable, within a capped number of operating hours. Very few zones in Europe meet this today, chiefly in northern Sweden.

A low-emission grid. If the zone's emission intensity is below 18 grams of CO2 equivalent per megajoule, additionality is not required, but renewable power purchase agreements and temporal and geographic correlation are. In practice this rule suits countries with a great deal of nuclear or hydropower.

The general case: three conditions together. All other producers, the large majority, must meet all three conditions that follow.

  • Additionality. The electricity comes from new renewable plants, commissioned no more than 36 months before the electrolyser, that have received neither operating nor investment aid. The point is that hydrogen should prompt new capacity, not take green power the grid already uses.
  • Temporal correlation. Until 31 December 2029 it is enough for renewable generation and hydrogen production to fall in the same calendar month. From 1 January 2030 they must fall in the same hour. Member States may introduce the hourly rule earlier, from 1 July 2027. The condition is deemed met in any hour in which the day-ahead price is at or below 20 euros per megawatt-hour.
  • Geographic correlation. The plant and the electrolyser are in the same bidding zone, or in an interconnected zone where the price is equal or higher, or the plant is in an interconnected offshore zone.

The transitional rule that has projects racing against 2028

Hydrogen plants that come into operation before 1 January 2028 are exempt from additionality until 1 January 2038. For ten years they may buy electricity from existing and from subsidised renewable plants. The exemption does not cover capacity added after that date. Because of this rule the commissioning date has a direct financial value, which is one reason investors watch construction schedules so closely.

Why the status matters: targets that create demand

RED III obliges Member States to secure demand for these fuels:

  • Industry. By 2030 at least 42 per cent of the hydrogen used in industry must be RFNBO, and at least 60 per cent by 2035. States may reduce the obligation by 20 per cent if they meet certain conditions, among them a low share of fossil hydrogen in consumption.
  • Transport. By 2030 advanced biofuels and RFNBO together should reach 5.5 per cent of energy in transport, of which at least one percentage point must be RFNBO.

A refinery, a fertiliser plant or a steelworks in the European Union cannot meet these quotas with just any "green" hydrogen, only with hydrogen that carries RFNBO certification. Hence the price difference: the buyer pays for the molecule and for compliance with a legal obligation. European Hydrogen Bank auctions require the same status.

How the status is proven

Compliance is confirmed by voluntary certification schemes recognised by the European Commission. In December 2024 the first three schemes for RFNBO were recognised: ISCC EU, CertifHy and REDcert. Certification follows the whole chain, from the power plant to the final buyer, on a mass-balance basis, with data entered in the Union Database. A project that does not keep hourly records of electricity generation and consumption from day one will later struggle to prove what it actually did.

What this means for Serbia and the region

The rules apply to the fuel, not to the country where it is made. Hydrogen or ammonia from outside the EU can obtain RFNBO status and count towards Member States' targets, provided it meets the same criteria and passes the same certification. For a producer in Serbia, Bosnia and Herzegovina or North Macedonia, three practical consequences follow.

  • Grid electricity alone does not qualify. Power systems dominated by coal are far from both the 90 per cent renewable threshold and the low-emission threshold. The realistic route is the general case: a new wind or solar plant without state support, a power purchase agreement, and proof of correlation.
  • Renewable support and RFNBO status exclude each other. A plant that has won an auction premium does not meet the additionality condition, except for hydrogen plants that start operating before 2028. This needs to be known before the financing structure is closed.
  • The buyer is in the EU, so the yardstick is European. National hydrogen rules may be lighter or absent, but an export project must be designed to Regulations 2023/1184 and 2023/1185, because that is how the certification body and the buyer will assess it.

What is changing: a revision under way

The rules are not final. In April 2026, in its AccelerateEU communication, the European Commission announced a targeted revision of the criteria in Regulation 2023/1184. Five Member States (Germany, Spain, the Netherlands, Austria and Poland) asked for the additionality transition and monthly correlation to be extended to 2035, and industry associations repeatedly called through the summer and autumn for the Commission to publish its proposal before the end of 2026. At the time of writing we had found no published proposal. The regulation separately requires the Commission to report by 1 July 2028 on the effects of the rules, including temporal correlation.

For an investor this means two things. The rules in force are the only ones that can be relied on today, so a project should meet them. At the same time the 2028 and 2030 dates may move, so the financial model should show both the scenario in which they do and the one in which they do not.

Five questions to ask before an investment decision

  • Exactly which plant supplies the electricity, when was it commissioned, and has it received state aid?
  • Can the project prove monthly correlation, and hourly correlation from 2030, and how many operating hours a year does that leave?
  • What is the total footprint, including compression, conversion to ammonia and transport, against the ceiling of 28.2 grams per megajoule?
  • Which recognised scheme will certify the project, and is the metering equipment included in the design?
  • Can the plant realistically start operating before 1 January 2028, and what happens to the project's economics if it is late?

Sources

Rules checked on 27 November 2026. This guide is for information and is not legal advice.