A feasibility study for a green hydrogen project has one question to answer: at what cost can the plant deliver a kilogram of hydrogen, and is there a buyer who will pay that price for long enough. Everything else, from the choice of technology to permits, feeds into that answer. This guide shows how the cost is calculated, using an example with its assumptions stated openly, and where studies most often go wrong.

What the cost is made of

The usual measure is the levelised cost of hydrogen, LCOH. It is the price per kilogram that covers all costs and the cost of capital over the life of the plant. It has three main parts:

  • Electricity. Consumption per kilogram multiplied by the price of power, including grid charges and levies.
  • Investment. The total value of the plant turned into an annual payment according to the cost of capital and the lifetime, then divided by annual production.
  • Operation and maintenance. Staff, water, servicing, insurance and replacement of electrolyser stacks, divided by annual production.

The first part depends on the price of electricity, the other two on how many hours a year the plant runs. Those two demands pull in opposite directions, and that is the core of every study.

An example: a 10 megawatt plant

The numbers that follow illustrate the method; they are not an offer or a market estimate. The assumptions are deliberately round:

  • electrolysis capacity of 10 megawatts;
  • consumption of 55 kilowatt-hours per kilogram, corresponding to the 60 per cent efficiency the International Energy Agency uses in its calculations;
  • 5,000 full-load hours a year, also the Agency's assumption;
  • total investment of 2,000 euros per kilowatt, so 20 million euros, the order of magnitude the Agency cites for alkaline plants outside China;
  • an electricity price of 60 euros per megawatt-hour, all charges included;
  • cost of capital of eight per cent, a 20-year life, annual operation and maintenance at three per cent of investment.

The calculation runs as follows. The plant uses 50,000 megawatt-hours a year and produces about 909 tonnes of hydrogen. Electricity costs 3.30 euros per kilogram. The annual payment on the investment is about 2.04 million euros, or 2.24 euros per kilogram. Operation and maintenance add 0.66 euros. Total: about 6.20 euros per kilogram.

What happens when operating hours change

If the same plant runs 3,000 hours instead of 5,000, it produces about 545 tonnes. The electricity cost per kilogram stays at 3.30 euros, but the investment payment is spread over fewer kilograms and rises to 3.74 euros, and operation and maintenance to 1.10 euros. Total: about 8.10 euros per kilogram.

This is the most important insight of the whole analysis. A solar plant in the region delivers the equivalent of a little over a thousand full-capacity hours a year, a wind farm two to three times that. An electrolyser tied to a single solar plant stands idle for most of the year. That is why projects combine wind and solar, oversize the power plant relative to the electrolyser, or buy additional energy through power purchase agreements.

For comparison, the European regulator ACER puts the cost of renewable hydrogen in the Union at about eight euros per kilogram, against just over two euros for hydrogen from natural gas. The example above lands in the same range, which suggests the price gap is not a matter of poor projects but of the basic arithmetic.

The RFNBO rules change the number of hours

If the hydrogen is to carry the renewable label and be sold to buyers in the Union, production must match the output of the contracted renewable plant: monthly until the end of 2029, and hourly from 2030. In practice hourly matching cuts operating hours or requires storage, and both raise the cost per kilogram. A study that assumes 5,000 operating hours after 2030 without explaining where the renewable electricity comes from in each of those hours is not finished. The rules and their possible revision are covered in the RFNBO guide.

The costs most often forgotten

  • Everything except the electrolyser. According to the International Energy Agency, more than half of total investment is engineering, construction, balance-of-plant equipment and contingency, not the stack. More in the guide to electrolysis.
  • Compression, storage and transport. The cost at the electrolyser outlet is not the cost at the buyer's gate. If the buyer is not on the same site, these costs can decide the project.
  • Stack replacement. The stack has a shorter life than the plant and is replaced at least once in twenty years.
  • Efficiency degradation. Electricity consumption rises as the stack ages, so guaranteed consumption at the end of stack life is worth more than the figure at the start.
  • Grid charges and levies. In some countries they are a significant part of the power price, and electrolysers are exempt in some places and not in others.
  • Water. A small cost by volume, but the abstraction permit and water treatment can determine the site.

Revenue: who pays the difference

Because green hydrogen costs more than fossil hydrogen, a project exists only if someone pays the difference. There are three possibilities, usually combined:

  • A buyer with an obligation. Refineries and industry in the Union must meet renewable hydrogen quotas, and importers of steel and fertiliser pay CBAM. For them the higher price replaces another cost.
  • Public support. Premiums per kilogram, grants and concessional loans. The guide to European funding gives an overview.
  • Secondary revenue. Sales of oxygen and heat, and services to the power system. Useful, but rarely decisive.

Banks require a long-term offtake agreement with a creditworthy buyer. Without one the project stays a study.

The order of checks before an investment decision

  • The buyer: who is it, how much do they need, at what price and for how many years?
  • The electricity: from which plants, at what price, for how many hours a year, and does it meet the RFNBO rules?
  • The site: grid connection, water, permits, distance from the buyer.
  • The technology: guaranteed consumption, availability and stack life, with supplier references.
  • The finances: sensitivity of the cost per kilogram to the power price, operating hours, investment and cost of capital.
  • The schedule: can the plant start operating before the dates on which the rules and the support depend?

A good study gives not a single price but a range, and an explanation of what moves it. If the cost per kilogram remains acceptable when power gets dearer and operating hours fall, the project is worth developing further.

Sources

Figures checked on 27 November 2026. The example illustrates the method with assumed inputs and is not an estimate for any specific project.