Greek company Hellenic Hydrogen applied in November 2026 to the Regulatory Authority for Waste, Energy and Water (RAAEY) for a hydrogen production certificate for a 25 MW plant, Greek business outlet Mononews reported on 19 November [1]. The plant would be located at the former Amyntaio–Filotas lignite power station, in the municipality of Amyntaio in the Western Macedonia region [1][2]. According to the application, installed and maximum capacity is 25 MW, and maximum hourly capacity is 14,900 kWh of thermal energy [1].

Hellenic Hydrogen was set up in January 2023 as a joint venture between oil company Motor Oil (51%) and PPC (49%), Greece's largest electricity utility [1][3]. The shareholders have not yet taken a final investment decision (FID), on which the final timetable and the start of works depend [1]. The Hellenic Competition Commission approved the joint venture in October 2022 to develop green hydrogen production, storage and trading projects [1]. Hydrogen would be produced by water electrolysis using renewable electricity [2].

Context. The application is the first phase of the wider North-1 project. The original plan envisaged a 50 MW electrolyser expandable to 200 MW, while the environmental permit amended in November 2026 covers 100 MW in total, in 20 independent units of 5 MW each [1]. Local outlet e-ptolemeos reports that the 100 MW plant could produce up to about 15.5 million kilograms of hydrogen a year, and that a 9.05 km pipeline operating at up to 90 bar is planned to connect to the DESFA network at Komnina [2]. The same outlet's headline cites an investment of EUR 70 million, without specifying which phase it covers [2]. The first potential customer is a new combined heat and power plant at the former Kardia lignite station, which would burn a blend of 80% natural gas and 20% hydrogen and supply district heating networks [1].

Link to the European Hydrogen Bank. The same 25 MW project has already been through an EU auction. In the third European Hydrogen Bank auction, whose results were published in May 2026, Hellenic Hydrogen placed the lowest successful bid in the general category for its 25 MW AN-1-B project in Amyntaio: EUR 0.57 per kilogram for 38,654 tonnes of hydrogen [4]. The auction selected nine projects in seven countries, close to 1.1 GW in total, with fixed premiums of EUR 0.57 to 3.49/kg, and grant agreements are expected in the last quarter of 2026 [5]. Under the auction terms, projects must reach financial close within two and a half years of signing and start operating within five years [5].

In our assessment, the application to RAAEY is therefore not a new announcement but a step the project must take to meet the deadlines tied to EU support. A low bid means the company asked for a small premium per kilogram on top of its other revenues; on its own it says nothing about the total cost of production. At the time of writing (27 November 2026) we found no public announcement that the grant agreement has been signed.

Why it matters. The project shows how the site of a closed lignite plant, with existing grid and gas connections, water and a skilled workforce, can be repurposed for hydrogen production [3]. The same question will arise in the Western Balkans' coal basins. A model in which a refiner and a power utility develop a project together, with an in-house cogeneration plant as first buyer, reduces offtake risk. Even so, as Serbia Energy notes, commercial progress depends on aligning renewable electricity supply, hydrogen sales and transport with the investment decision [3].

Who it matters to. Power utilities and oil companies in the region, municipalities in coal basins, gas transmission operators considering hydrogen blending, and just transition funds.

What comes next. RAAEY has to rule on the application and the shareholders on the investment. Serbia Energy notes that a certificate application alone does not set a construction start or a date for first deliveries [3].

Sources

  1. Mononews, ‘Hellenic Hydrogen: Για 25MW η νέα αίτηση στη ΡΑΑΕΥ για μονάδα πράσινου υδρογόνου στο Αμύνταιο’, 19 November 2026. https://www.mononews.gr/business/hellenic-hydrogen-gia-25mw-i-nea-aitisi-sti-raaef-gia-monada-prasinou-ydrogonou-sto-amyntaio
  2. e-ptolemeos.gr, ‘Αμύνταιο: Αίτηση για μονάδα πράσινου υδρογόνου 25 MW στον πρώην ΑΗΣ – Επένδυση 70 εκατ. ευρώ’, 22 November 2026. https://e-ptolemeos.gr/amyntaio-aitisi-gia-monada-prasinoy-ydrogonoy-25-mw-ston-proin-ais-ependysi-70-ekat-eyro
  3. Serbia Energy, ‘Hellenic Hydrogen seeks approval for 25 MW plant at former Greek coal site’, 20 November 2026. https://serbia-energy.eu/hellenic-hydrogen-seeks-approval-for-25-mw-plant-at-former-greek-coal-site/
  4. Balkan Green Energy News, "Hellenic Hydrogen wins European Hydrogen Bank grant with lowest bid", 8 May 2026. https://balkangreenenergynews.com/hellenic-hydrogen-wins-european-hydrogen-bank-grant-with-lowest-bid/
  5. H2 Tech (European Commission announcement), "EU awards over €1 billion to European hydrogen projects to accelerate the clean transition", May 2026. https://h2-tech.com/news/2026/05-26/eu-awards-over-1-billion-to-european-hydrogen-projects-to-accelerate-the-clean-transition/