From 1 January 2030, hydrogen produced by electrolysis in the European Union will count as a renewable fuel of non-biological origin (RFNBO) only if the renewable electricity used to make it is matched with the electrolyser's consumption on an hourly basis, rather than a monthly one [1][2]. The Commission adopted this rule in 2023 in Delegated Regulation (EU) 2023/1184. Three and a half years before it applies, it is open again: in April 2026 the Commission announced a targeted review, earlier than the legislation foresaw [2][3].
This text does not announce a rule change. At the time of writing (27 November 2026) the editorial team had found no published proposal for an amended regulation, and the latest available source says no proposal had been published by 12 October 2026 [2]. What exists are requests from member states and industry, opposing positions from non-governmental organisations and several quantitative estimates. For projects in Serbia and the region that target exports to the EU, the question is not only what Brussels will decide, but how to design a plant while the rules are not final.
What the rules require today
Delegated Regulation 2023/1184 sets three main conditions for grid electricity used by an electrolyser to count as fully renewable [1][7]:
- Temporal correlation. Until 31 December 2029 it is enough for renewable generation and electrolyser consumption to match within the same calendar month. From 1 January 2030 matching must be hourly [2][4][7]. The condition is also deemed met when the day-ahead price is at or below EUR 20 per MWh, or below 0.36 times the price of an EU ETS allowance [2][7].
- Additionality. The renewable plant under the purchase agreement must have started operating no earlier than 36 months before the electrolyser and must not receive operating or investment aid, other than support for land or grid connection [2][7][9]. Electrolysers that start operating before 1 January 2028 are exempt from this condition until 1 January 2038 [2][3][4][7].
- Geographic correlation. The renewable plant must be in the same bidding zone as the electrolyser, in an interconnected offshore zone, or in an interconnected zone with an equal or higher day-ahead price [2][7].
There are two important exemptions. Electrolysers in a bidding zone where the renewable share exceeded 90 percent in the previous year can count grid electricity as renewable [2][9]. In zones where grid emission intensity is below 18 gCO2eq/MJ the additionality condition does not apply, but the purchase agreement and temporal and geographic correlation remain [7]. In addition, the fuel must achieve emission savings of at least 70 percent compared with the fossil comparator of 94 gCO2eq/MJ, under the methodology in Delegated Regulation (EU) 2023/1185 [8][9].
Why the rule is open before its deadline
The Renewable Energy Directive required the Commission to report on this methodology by 1 July 2028 [2][8]. According to the sources reviewed, the Commission brought the review forward in April 2026, as part of a package of measures to speed up the transition [2][3]. The sources differ on the name of the document and the exact date: HYZEN cites the AccelerateEU communication of 22 April 2026, Capstone cites the "One Europe, One Market" roadmap of 24 April 2026, and EDF Europe places the same communication in May [2][3][4].
The initial target for a proposal was June 2026. According to HYZEN, Director-General for Energy Céline Gauer told the European Parliament on 14 July 2026 that the review would come "in the autumn" [2]. Because this is a delegated act, Parliament and Council cannot amend it, only reject it within two to four months of adoption [3]. Even if a proposal were published by the end of 2026, the new rules could in practice apply only during 2027.
The background is economic. According to a study commissioned by EDF Europe, electrolytic hydrogen production in the EU was below 50 thousand tonnes in 2024 [5]. EDF Europe says that 571 MW of electrolysers had been installed in the EU by mid-2025, with about 2.84 GW under construction [4]. That is far from the Directive's targets, under which 42 percent of hydrogen used in industry should come from RFNBOs by 2030 and 60 percent by 2035 [10]. Investors and member states argue that strict electricity sourcing rules raise prices and delay investment decisions. Opponents reply that the costs are overstated and the risk of higher emissions understated.
What member states and industry are asking for
According to a review published by HYZEN, member states proposed in March 2026 that the start of additionality be moved to 2035, with up to ten years of protection for existing projects, and that monthly matching remain in place after 2030 for lower-emission grids [2]. In letters from July and September 2026, industry asked for additionality to be postponed to 2035, for monthly matching to be kept or at least for hourly matching to be postponed to 2035, and for the exemption threshold to be lowered from 90 to 80 percent renewables [2].
The German energy and water association BDEW argued as early as March 2025 that the current rules raise production costs by about EUR 2.40 per kilogram of hydrogen and proposed introducing additionality only from 2035 [6]. Capstone, a Washington consultancy, in its May 2026 forecast expects the Commission to postpone both additionality and hourly matching to 2032 or 2033, with protection for existing projects extended to at least 2040 [3]. That is one firm's forecast, not a Commission position.
What cost and emissions estimates show
Estimates of the rules' impact on the price of hydrogen differ by an order of magnitude, so they should be read together with their methodology:
- BDEW (March 2025): about EUR 2.40 per kilogram of additional cost from the rules [6].
- Capstone (May 2026): the RFNBO hydrogen price could fall by about EUR 2 per kilogram, from about EUR 6 to about EUR 4, if deadlines are postponed; the source gives no methodology [3].
- EDF Europe (July 2026), citing work by Hordvei and colleagues and EWI from 2025: the requirements add about EUR 0.30 to 0.35 per kilogram at system level, and the overall "green premium" is below EUR 1 per kilogram [4].
- CLIMACT, Systemik and the University of Liège for EDF Europe (September 2026): postponing the conditions lowers the EU weighted-average cost of hydrogen production by EUR 0.10 to 0.25 per kilogram in 2035 and raises output by 0.4 to 0.5 million tonnes [5].
The same CLIMACT study also estimates the cost of postponement: electricity prices up to 1.8 percent higher in 2035, EUR 1.7 to 3.2 billion less investment in renewables over 2025–2050, and about 20 to 68 million tonnes of additional CO2 equivalent emissions [5]. A combination of postponement and a looser exemption threshold leads, according to the study, to EUR 9 billion less renewable investment and about 90 million tonnes of additional emissions [5]. The authors note the limits themselves: the baseline applies additionality from 2030 without protection for existing projects, which is stricter than the current regulation, and hourly matching is modelled in two-hour steps [5].
EDF Europe also cites work by Zeyen and colleagues from 2024, according to which emissions in Germany in 2030 without temporal matching would be about 10 to 30 kilograms of CO2 per kilogram of hydrogen [4]. BDEW, on the other hand, argues that without monthly correlation emissions in 2030 would be about 20 percent higher, citing a study by the German economy ministry [6]. In the editorial team's assessment, this range shows that the debate is not a technical detail: the choice between monthly and hourly matching decides whether an electrolyser reduces or increases emissions in the grid where it operates.
What it means for Serbia and the region
The delegated regulation's rules do not apply only to production in the EU. RFNBOs can be produced in any country, provided the producer proves compliance with the same criteria through a certification scheme recognised by the Commission [8]. For third countries the regulation allows equivalent concepts of a bidding zone, and if the grid has no geographically differentiated prices, the whole country can be treated as a single zone [9]. According to a GIZ guide from February 2026, the recognised schemes for RFNBOs are ISCC, CertifHy and REDcert [8].
For Serbia this has two practical consequences. The first is that the exemption for grids with more than 90 percent renewables or low emissions is not available: according to the Energy Community, the default CBAM emission factor for electricity from Serbia is 1.041 tonnes of CO2 per MWh, and coal-fired generation in the second quarter of 2026 was 6.54 TWh [11]. An electrolyser in Serbia producing hydrogen for export must therefore rely on a purchase agreement with a new renewable plant and on matching in time. The second is that hourly matching, if it stays in 2030, will require the electrolyser to run mostly when the contracted solar or wind plant is producing, or to have storage, which changes the utilisation factor and the price of hydrogen.
The region is only at the start. According to Balkan Green Energy News, Serbia was carrying out its first green hydrogen pilot project with Germany in November 2024 [12]. Serbia planned to couple its day-ahead market with the EU via the borders with Hungary and Bulgaria by the fourth quarter of 2026 [13]. In the editorial team's assessment, for projects whose investment decision is realistically possible only after 2028, the additionality exemption until 2038 is not available anyway, so the key question for them is precisely hourly matching.
Who this matters to
- Development teams at utilities and renewable investors in Serbia, Montenegro, Bosnia and Herzegovina and North Macedonia considering electrolysis alongside solar and wind plants: the structure of purchase agreements and the sizing of storage depend on which version of the rules applies at commissioning.
- Industrial hydrogen buyers in the region and in neighbouring EU states, such as refineries and fertiliser producers, which must meet the 42 percent RFNBO quota in industry by 2030 [10].
- Banks and development institutions assessing projects: the gap between estimates of EUR 0.10 and 2.40 per kilogram means a financial model must include scenarios for both variants.
- Energy ministries aligning legislation with the EU acquis through the Energy Community.
What to watch
- Publication of the proposed amended delegated regulation and the public consultation that industry expects to last at least four weeks [2].
- Whether hourly matching will be postponed, and until when, and whether protection for existing projects will be extended beyond 2038 [2][3].
- Whether the exemption threshold will be lowered from 90 to 80 percent, which would benefit countries with a lot of hydropower [2][5].
- Whether the European Parliament or Council will use their right to reject the act within two to four months [3].
- Whether Serbia, Montenegro and the other Energy Community contracting parties will take over the RFNBO methodology in domestic legislation, and which certification schemes domestic producers will use.
Editorial conclusion. In the editorial team's assessment, projects in the region should not build a financial model on the assumption that hourly matching will be postponed. If the rule is relaxed, the project gains; if it stays, a project planned from the outset for the stricter variant has lost nothing.
Sources
- Commission Delegated Regulation (EU) 2023/1184 on the methodology for renewable fuels of non-biological origin. https://eur-lex.europa.eu/eli/reg_del/2023/1184/oj
- HYZEN Energy, "RFNBO Delegated Act Revision 2026: What Could Change", updated 12 October 2026. https://www.hyzenergy.com/blog/rfnbo-delegated-act-revision-2026
- Capstone DC, "The European Commission's Hydrogen Pivot", 20 May 2026. https://capstonedc.com/insights/the-european-commissions-hydrogen-pivot/
- Environmental Defense Fund Europe, "Evidence for an Effective RFNBO Review", 1 July 2026. https://www.edfeurope.org/news/2026/01/07/evidence-effective-rfnbo-review-0
- CLIMACT, Systemik (UCLouvain) and ULiège for EDF Europe, "Impact of RFNBO delegated act regulatory variants", September 2026. https://table.media/assets/documents/261015-edf-final-report_impact-of-rfnbo-delegated-act-regulatory-variants.pdf
- BDEW, "Amendments to the electricity sourcing criteria in the Delegated Act on RFNBO", 20 March 2025. https://www.bdew.de/media/documents/BDEW-Position_Paper_Electricity_Purchasing_Criteria_DA_RFNBO_final_en.pdf
- Rabobank, "Hydrogen in Europe, part 2: What are renewable fuels of non-biological origin?", 29 August 2024. https://www.rabobank.com/knowledge/d011439292-hydrogen-in-europe-part-2-what-are-renewable-fuels-of-non-biological-origin
- GIZ H2Uppp, "EU RFNBO Certification Compendium", February 2026. https://ptx-hub.org/wp-content/uploads/2026/03/H2Uppp_EU-RFNBO-Compendium_2026.pdf
- Ecologic Institute and PtX Hub, "FAQ: EU requirements for green hydrogen and PtX", October 2023. https://www.ecologic.eu/sites/default/files/publication/2024/60022-FAQ-EU-requirements-green-hydrogen-and-PtX.pdf
- European Hydrogen Observatory (Clean Hydrogen Partnership), "The European hydrogen policy landscape", January 2026. https://ipcei.observatory.clean-hydrogen.europa.eu/sites/default/files/2026-01/The%20European%20hydrogen%20policy%20landscape_January%202026_v2.pdf
- Energy Community Secretariat, "CBAM Quarterly report 2026/2", 27 July 2026. https://www.energy-community.org/dam/jcr:849e0116-9c54-44d5-a583-4eb8d0c85076/EnCS_CBAM_Quarterly_Report_2026_2.pdf
- Balkan Green Energy News, "Serbia implementing first green hydrogen pilot project with Germany", 1 November 2024. https://balkangreenenergynews.com/?p=75502
- Argus Media, "Serbia aims to couple its electricity market in 4Q26", 14 February 2025. https://www.argusmedia.com/en/news-and-insights/latest-market-news/2658170-serbia-aims-to-couple-its-electricity-market-in-4q26