Croatian oil company INA, majority-owned by Hungary's MOL, announced in early July 2026 that all civil and installation works on an 11 MW peak solar plant at its Rijeka oil refinery had been completed [5][6]. The plant will power a 10 MW electrolyser, whose installation is under way and due to be completed by the end of 2026, with first green hydrogen planned for 2027 [5][6]. According to the company, the facility will produce about 1,500 tonnes of green hydrogen a year [5][6].
This is not news of production starting. Before commissioning, the solar plant still has to pass final testing and technical verification, and the electrolyser is not yet finished [5][6]. Earlier reports that the project is entirely self-financed are incorrect: it is co-financed from Croatia's National Recovery and Resilience Plan (NRRP) [1][5].
Financing. According to the European Commission's page on Recovery and Resilience Facility projects, the EU contribution is EUR 15 million, for a new 10 MW facility producing renewable hydrogen by electrolysis combined with a solar plant [1]. INA says the completion of mechanical works fulfils its initial contractual obligations under that agreement [6]. The total investment, according to the July 2026 announcement, is about EUR 61 million [5][6].
Project history. The project has changed contractors since it was first announced. In April 2024 INA said key equipment would be supplied by Ivicom Consulting [2], and in May 2024 US-Croatian company Ohmium announced that Ivicom had selected it as supplier of 10 MW of PEM electrolysers [3]. Ohmium described this only as a selection, with no contract announced [3]. In December 2025 INA signed two new contracts worth more than EUR 33 million in total: with Končar and Siemens Energy for the hydrogen production and distribution facility, worth EUR 22.5 million excluding VAT, and with Končar for the 11 MW solar plant, worth almost EUR 11 million excluding VAT [4]. Končar is the main contractor [4][5]. The sources do not explain what happened to the original arrangement, or who manufactured the electrolyser that, according to BGEN, INA had secured earlier [4]. The gap between EUR 33 million in December 2025 and EUR 61 million in July 2026 is also unexplained; the second figure may include previously contracted equipment, but that is our assessment.
The project is part of a wider package: in April 2024 INA said that its total investment in hydrogen in Rijeka and a biomethane plant in Sisak, built on a turnkey basis by Austria's Biogest, amounted to EUR 98 million, and that both plants should be completed during 2026 [2]. In our assessment, moving first hydrogen to 2027 means a delay of about a year against the original plan.
Why it matters. In our assessment, this is the closest example of a commercial green hydrogen plant at a refinery in Serbia's immediate neighbourhood. The hydrogen is intended mainly for transport and partly for refinery processes [5][6], so the project will also depend on how refuelling infrastructure develops in Croatia. BGEN describes the Croatian hydrogen market as being at an early stage of development [4]. Ohmium noted in 2024 that Croatia's hydrogen strategy envisages 70 MW of production capacity by 2030 [3]; the Rijeka plant would be about a seventh of that target. MOL, INA's majority owner, commissioned its own 10 MW electrolyser in Hungary in April 2025 [4].
Who should pay attention. Refineries and industrial users of grey hydrogen in the region assessing a similar model; transport operators and cities considering hydrogen vehicles; regional contractors, since the main contractor is a regional company; and ministries using recovery plan funds, as an example of how those deadlines are tied to contractual phases.
What to watch. Whether the electrolyser is installed by the end of 2026 as announced, and when the solar plant receives its operating permit. At the time of writing (27 November 2026) we found no announcement that the electrolyser has been completed. The first real indicator will be actual production and the hydrogen price in 2027.
Sources
- European Commission, Recovery and Resilience Facility, "New hydrogen production capacity installed" (Croatia), accessed 27 November 2026. https://reforms-investments.ec.europa.eu/projects/new-hydrogen-production-capacity-installed_en
- Balkan Green Energy News, "INA potpisala ugovore o gradnji postrojenja za zeleni vodonik i biometan", 16 April 2024. https://balkangreenenergynews.com/rs/ina-potpisala-ugovore-o-gradnji-postrojenja-za-zeleni-vodonik-i-biometan
- Ohmium International (Business Wire), "Ohmium Selected to Provide 10MW PEM Electrolyzers for First Green Hydrogen Project in Croatia", 20 May 2024. https://www.businesswire.com/news/home/20240520820657/en/Ohmium-Selected-to-Provide-10MW-PEM-Electrolyzers-for-First-Green-Hydrogen-Project-in-Croatia
- Balkan Green Energy News, "Siemens Energy i Končar će instalirati elektrolizer za kompaniju INA", 8 December 2025. https://balkangreenenergynews.com/rs/siemens-energy-i-koncar-ce-instalirati-elektrolizer-za-kompaniju-ina/
- Balkan Green Energy News, "INA izgradila solarnu elektranu kojom će napajati postrojenje za zeleni vodonik", 3 July 2026. https://balkangreenenergynews.com/rs/ina-izgradila-solarnu-elektranu-kojom-ce-napajati-postrojenje-za-zeleni-vodonik/
- Hydrogen Central (INA announcement), "First phase of commercial green hydrogen production plant at Rijeka Refinery completed", 8 July 2026. https://hydrogen-central.com/first-phase-of-commercial-green-hydrogen-production-plant-at-rijeka-refinery-completed/