Croatia's Končar Group announced on 20 October 2026 that its KONČAR NEXUS project had been selected among European Union Innovation Fund projects, with expected co-financing of EUR 39,292,253 [1]. The project concerns the industrialisation of the KONČAR Smart Power Interface (KSPI), a modular 2.5 MW platform that converts electricity from the medium-voltage grid into direct current, primarily to power electrolysers [1].
It is worth being clear about what this news is and what it is not. Končar is not building an electrolyser or a hydrogen production plant. This is power electronics equipment that sits between the grid and the electrolyser, a part of the supply chain that hydrogen news rarely mentions. Nor has the grant been finally awarded: according to Končar, the final award depends on successful completion of the preparation phase and signature of the contract [1].
According to Končar, the basic production module is called the KONČAR Smart Power Module (KSPM) and is based on solid-state transformer technology [1]. It is a containerised unit that combines in a single assembly the medium-voltage connection, protection, power conversion, galvanic isolation, auxiliary supply, liquid cooling, and digital monitoring and control [1]. Končar says this was its first application to the Innovation Fund and that the project also received the STEP Seal, a label the European Commission awards after a positive evaluation by independent experts [1].
Balkan Green Energy News (BGEN), citing project data, reports planned capital expenditure of up to EUR 70.7 million, a plant in Sesvetski Kraljevec producing up to 200 units a year, financial close scheduled by 31 March 2029 and operations starting on 1 January 2031 [2]. According to the same source, engineering, a validation laboratory and a 110 kV substation would be located at the Fallerovo site [2]. Končar's announcement does not give these figures, so they should be read as project data reported by BGEN. In the same article, BGEN's subheading also mentions EUR 70.1 million, which does not match the figure in the body of the text [2].
In this round, the European Commission selected 77 projects from 23 European countries, with total funding of EUR 3.4 billion [1][3]. According to Končar, the call received 358 applications, with requested funding six times the available budget [1]. Končar's announcement does not name the call, so neither do we.
Končar is not new to hydrogen. According to BGEN in December 2025, INA contracted Siemens Energy and Končar for a 10 MW green hydrogen production and distribution plant at the Rijeka refinery, estimated at EUR 22.5 million excluding VAT, as well as an 11 MW solar plant built by Končar, worth almost EUR 11 million excluding VAT [4]. The plant is expected to produce around 1,500 tonnes of green hydrogen a year [4]. Separately, the European Bank for Reconstruction and Development (EBRD) has approved a loan of up to EUR 120 million to Končar for new production capacity for grid equipment, as part of a EUR 370 million investment cycle [5]. That loan is not related to hydrogen.
In the region, hydrogen is mostly reported through production projects: how many megawatts, where and when. This news shows the other side of the market, industrial equipment. An electrolyser cannot operate without equipment that converts grid power into direct current at the right voltage. The fact that a company from the region has won European support for series production of such equipment means the region can take part in the hydrogen economy as an equipment manufacturer, not only as a location for projects. That is the editors' assessment.
The timeframe also matters. If the deadlines reported by BGEN are met, series production would begin in 2031 [2], after 2030, the year for which the EU has set its renewable hydrogen targets. The product's success will depend on how much electrolysis is actually built in Europe, and that remains an open question.
The news matters to electrolysis project developers in Croatia, Serbia and the wider region, for whom a regional equipment supplier could shorten the supply chain; to electrolyser manufacturers, as potential partners or competitors; to distribution and transmission system operators, because the device connects at medium voltage; and to industrial companies in the region considering Innovation Fund applications, as an example that a first application can succeed.
The key next step is signature of the grant agreement, which Končar describes as a condition for the final award [1]. After that, it will be worth following the decision to build the plant, financial close, scheduled by the end of March 2029 [2], and the first customer contracts. At the time of writing (27 November 2026) we had not found an official European Commission release listing the selected projects, so the project details rely on Končar's announcement.
Sources
- KONČAR, ‘KONČAR NEXUS selected among European Union Innovation Fund projects’, 20 October 2026. https://www.koncar.hr/en/news/koncar-nexus-selected-among-european-union-innovation-fund-projects
- Balkan Green Energy News, ‘Končar secures EUR 40 million EU grant for green hydrogen technology’, 23 October 2026. https://balkangreenenergynews.com/koncar-secures-eur-40-million-eu-grant-for-green-hydrogen-technology/
- S&P Global, ‘EU commits €3.4B to 77 net-zero technology projects’, 19 October 2026. https://www.spglobal.com/energy/en/news-research/latest-news/energy-transition/101926-eu-commits-34b-to-77-net-zero-technology-projects
- Balkan Green Energy News, ‘Siemens Energy, Končar to install electrolyzer, solar power plant for INA’, 9 December 2025. https://balkangreenenergynews.com/siemens-energy-koncar-to-install-electrolyzer-solar-power-plant-for-ina/
- EBRD, ‘EBRD backs new production capacities of critical electricity infrastructure equipment in Croatia’, 2026. https://www.ebrd.com/home/news-and-events/news/2026/ebrd-backs-new-production-capacities-of-critical-electricity-inf.html