OMV Petrom announced on 28 August 2026 that it had completed a 20 MW electrolyser project at its Petrobrazi refinery in Romania, financed under Romania's National Recovery and Resilience Plan (PNRR) [1]. On 3 August 2026 the European Investment Bank (EIB) approved proposed financing of around EUR 165 million for two electrolysers at the same refinery, of 20 MW and 35 MW, with a total cost of around EUR 239 million [2]. According to the Romanian news agency Agerpres, the two plants together are expected to produce around 8,000 tonnes of green hydrogen a year [3]. Their combined capacity is 55 MW [2][3]. The sources we reviewed give no exact start-up dates for either plant.
For the region, what matters is what the hydrogen is for. According to the company and Agerpres, it will be used to produce sustainable aviation fuel (SAF) and hydrotreated vegetable oil (HVO) [1][3]. None of the sources we reviewed says that electrolytic hydrogen will replace grey hydrogen in refinery processes.
According to the company's press release, the 20 MW project was implemented between 2 September 2023 and 31 August 2026 on the Petrobrazi refinery platform in Brazi, Prahova county [1]. The total project value is RON 215,722,562.45, eligible costs RON 111,681,846.40, and the maximum non-reimbursable support RON 103,309,500 [1]. Agerpres and Romania Insider put that support at around EUR 21 million [3][4]. The financing contract was signed on 29 December 2023 under PNRR investment I.2 [1].
The electrolysis equipment is supplied by the German company Neuman & Esser, while site works and integration are carried out by Kraftanlagen Romania with local partners [3]. The first module was delivered in March 2026, and the remaining three were due in the following months [3][4]. The company says the plant will use electricity exclusively from renewable sources [1]. The sources do not mention a power purchase agreement or a specific plant that will supply the electrolyser.
According to Agerpres, the 20 MW electrolyser is expected to produce around 3,000 tonnes of green hydrogen a year [3]. The second, 35 MW electrolyser is part of the same programme, but the sources give no commissioning date for it [2][3]. On the EIB website the project is listed as approved, with the bank's caveat that project data are indicative until the contract is signed [2]. The environmental impact assessment is dated 17 July 2026 [2].
Hydrogen from Petrobrazi is part of a wider OMV Petrom programme worth EUR 750 million. Of that, EUR 560 million is for an SAF and HVO unit with a capacity of 250,000 tonnes a year, and EUR 190 million for the two hydrogen units [3][4]. Construction of the SAF and HVO unit began in 2025, with production planned to start in 2028 [3][4]. According to Agerpres, these fuels can cut CO2 emissions by at least 65% over their full life cycle [3]. That figure is as reported by Agerpres, not an independent assessment.
It also matters what the sources do not confirm. The 28 August press release refers to completion of the project within the PNRR financing period [1]. At the time of writing (27 November 2026) we had found no confirmation that the plant has started regular hydrogen production. Romania Insider's headline says the first module was "commissioned", but the text below it describes only the delivery of the module [4]. We therefore regard the plant's operating status as unconfirmed.
For readers in Serbia and the region, the project is an example of electrolysis financed through a combination of EU grants and an EIB loan, at an existing refinery that already has an offtaker, a grid connection and a site. A model in which hydrogen goes into aviation and transport fuels, rather than being sold on an open market, reduces the risk of having no buyer. That is the editors' assessment. Serbia has no access to PNRR funds, so the model does not apply directly, but it shows what kind of projects the EIB is financing next door.
In the coming months it is worth watching for confirmation that the 20 MW plant has started production, for the signing of the EIB financing contract, and for the timeline of the 35 MW electrolyser.
Sources
- OMV Petrom, press release on completion of the 20 MW PNRR green hydrogen production project (PDF), 28 August 2026. https://www.omvpetrom.com/downloads/2026/08/7b13f6ea-1c11-ddd3-1d1a-c62452f40202/20%20MW%20Comunicat%20Presa%20PNRR%20H2%20ENG.pdf
- European Investment Bank, ‘Petrobrazi Green Hydrogen Production’, project 20250483, approved 3 August 2026. https://www.eib.org/en/projects/pipelines/all/20250483
- Agerpres, ‘First module for green hydrogen production at Petrobrazi refinery delivered’, 17 March 2026. https://agerpres.ro/2026/03/17/first-module-for-green-hydrogen-production-at-petrobrazi-refinery-delivered--1538025
- Romania Insider, ‘First 20 MW module for OMV Petrom’s green H2 project facility commissioned’, 19 March 2026, updated 12 August 2026. https://www.romania-insider.com/first-module-green-hydrogen-petrobrazi-omv-petrom-2026