Swedish company Stegra, which is building a steel plant in Boden based on hydrogen from electrolysis, needs at least two billion dollars in additional financing to complete the plant, according to sources cited by Bloomberg [2]. The same amount, more than 20 billion Swedish kronor, was reported on 24 November 2026 by the Swedish daily Svenska Dagbladet [5]. Stegra has not confirmed the amount and said it is working with shareholders and lenders [2].
This is not news of the project's collapse, but of how much a first project of its kind costs. Only five months ago Stegra completed a EUR 1.4 billion round that was meant to cover the completion of construction [1][2][3]. According to Bloomberg, the parties now want to secure financing by mid-December [2].
From rescue to a new gap
On 14 April 2026 Stegra announced it had agreed in principle on EUR 1.4 billion in new financing from new and existing investors [1]. The round was led by a Wallenberg Investments consortium with Singapore's Temasek and the IMAS foundation, alongside existing shareholders Altor, Hy24 and Just Climate [1]. The money was intended to complete construction, cover increased project costs and provide a financial buffer, and the company said at the time that "the project timeline is under review" [1]. Then chief executive Henrik Henriksson said the financing "reflects the strong conviction in Stegra's business model among new and existing investors, as well as lenders" [1].
In mid-May lenders, including the European Investment Bank, BNP Paribas, ING and KfW IPEX-Bank, agreed to unlock about EUR 1.5 billion of unused credit lines, according to GMK Center citing Bloomberg [4]. According to secondary sources, the EUR 1.4 billion round was completed in June, when the board also changed [2][3].
By the end of September it was clear this was not enough. On 30 September Stegra announced that chief executive Henriksson was leaving and that Håkan Buskhe would lead the company from 1 November [3]. A review carried out by the new owners and board with external consultants found that completion costs were significantly higher than the summer estimate [3]. According to SteelOrbis, Stegra attributed this mainly to inflation and the additional costs of accelerating construction [2]. The Swedish business weekly Affärsvärlden then put the shortfall at at least 10 billion kronor [3].
According to Svenska Dagbladet, board chair Leif Johansson partially confirmed the need for more capital, describing the situation as fluid [5]. According to Bloomberg, options under consideration include additional equity from existing shareholders, public support, new borrowing, more flexibility from lenders, asset sales and strategic partnerships, and Wallenberg Investments is expected to play a key role in the negotiations [2].
How much the project has grown
According to GMK Center, the original plan foresaw construction worth 25 billion kronor and production starting in 2024, while total capital raised, including loans and the new shortfall, would reach about 100 billion kronor [3]. According to the same source, the company's latest statement moves production to early 2027, with the timeline again under review [3]. The plant includes 740 MW of electrolysis [6]. According to Canary Media, before the crisis Stegra had raised about EUR 6.5 billion in loans and equity and planned to complete construction by the end of 2026 [7]. According to the same source, the plant was about 60 percent complete in autumn 2025 [7].
Who this matters to
In the editorial team's assessment, the Stegra case matters to anyone in the region considering green steel, ammonia or another large-scale industrial use of hydrogen. It shows that for first projects the risk is not only technology, but also construction, infrastructure and financing in a period of inflation. For banks and development institutions financing industrial projects in Serbia and the region, it means closer attention to cost-overrun reserves and phased construction.
What to watch
The most important deadline is mid-December 2026, by which the parties, according to Bloomberg, want to secure new financing [2]. It is also worth watching whether Stegra will publish an official amount and a new date for the start of production, and whether the Swedish state or the EU will take part in a new round. At the time of writing (27 November 2026) Stegra had not published the amount it is missing.
Sources
- Stegra, "Stegra has agreed in principle on a €1.4 billion financing round", 14 April 2026. https://stegra.com/en/news-and-stories/stegra-has-agreed-in-principle-on-a-14-billion-financing-round
- SteelOrbis, "Stegra needs at least $2 billion in additional financing to complete Boden plant", 26 November 2026. https://www.steelorbis.com/steel-news/latest-news/stegra-needs-at-least-2-billion-in-additional-financing-to-complete-boden-plant-1493764.htm
- GMK Center, "Stegra again requires additional funding for the construction of a green plant", 1 October 2026. https://gmk.center/en/news/stegra-requires-additional-funding-for-the-construction-of-a-green-plant/
- GMK Center, "Stegra has secured access to €1.5 billion in loans to complete the construction of the plant", 14 May 2026. https://gmk.center/en/news/stegra-has-secured-access-to-e1-5-billion-in-loans-to-complete-the-construction-of-the-plant/
- News Minimalist, citing Svenska Dagbladet, "Stegra needs $2 billion more to finish Boden steel plant", 24 November 2026. https://www.newsminimalist.com/articles/stegra-needs-dollar2-billion-more-to-finish-boden-steel-plant-b9c7839d
- Mining & Metal News, "Stegra raises €1.4bn as Boden project faces delays", 15 April 2026. https://www.miningmetalnews.com/20260415/3396/stegra-raises-eu14bn-boden-project-faces-delays
- Canary Media, Maria Gallucci, "Stegra lands funding to complete world's first major green-steel mill", 14 April 2026. https://www.canarymedia.com/articles/green-steel/stegra-funding-complete-mill