In early September 2026, Elektroprivreda Srbije (EPS) issued a public call inviting companies and investors to sell it renewable energy projects or develop them jointly [1]. Most coverage read the call as a story about solar and wind. For the hydrogen market, the more significant part is the second, less visible half: Serbia's largest power producer explicitly invited partners to co-develop green hydrogen production projects on its own sites [1][2].
The call is not an investment decision. It sets out no capacities, no budget and no construction timeline. It is nonetheless the first concrete institutional signal that hydrogen in Serbia is moving from conference panels towards a discussion of sites, infrastructure and partnership models. This analysis examines what EPS has offered, the context the call comes from, which constraints remain unresolved and who should pay attention.
What EPS announced
According to the EPS statement of 8 September 2026, the call was published in the daily newspaper Politika and on the company's website and is open to legal entities [1]. Chief executive Dušan Živković described its purpose as diversifying the EPS portfolio through a transparent and competitive process [1].
The call is split into two groups of projects that follow quite different logic:
- Group 1 covers solar, wind and hybrid projects of at least 50 MW installed capacity connected to the transmission system. Battery storage is not mandatory but earns additional credit. Here EPS uses a two-phase competitive procedure to select projects it may acquire [1][2].
- Group 2 covers projects using biomass and municipal, industrial or organic waste to generate electricity or heat, as well as green hydrogen production. For this group, EPS offers partners existing sites and infrastructure for joint project development [1].
Group 2 was open for 30 days. According to EPS, the company will then define concrete cooperation models based on the interest expressed [1]. Balkan Green Energy News adds that EPS will decide within a maximum of 60 days whether to issue detailed documentation or cancel the procedure, and will notify all participants accordingly [2].
Hydrogen on power plant sites
The most concrete element of Group 2 is the sites. EPS is offering partners existing locations and infrastructure, including the sites of the Morava and Kolubara A thermal power plants [1]. These are ageing coal-fired plants [3], which means they already have what a new project finds hardest to secure: land designated for energy use, a grid connection, water and industrial infrastructure.
Živković singled out this point, saying it is particularly important that EPS can put its existing infrastructure to work for new energy projects [1]. For electrolysis this is far from incidental. An electrolyser needs a strong and reliable grid connection, substantial volumes of treated water and, as a rule, proximity to offtakers or transport infrastructure. Sites that already offer all of this shorten project development and reduce permitting risk.
The call does not say which partnership model EPS would accept, whether a joint venture, a site lease, a power purchase agreement or some combination, nor how much capacity the sites could host. Those questions are left to the second phase of the procedure.
From analysis to call
The call did not come out of nowhere. In March 2025, at the 2nd Belgrade International Conference on Hydrogen, Živković announced that EPS was analysing the production and use of green hydrogen, including as an alternative fuel in its thermal power plants [4]. The analysis was meant to identify potential sites, facility size and uses [4].
Aleksandar Latinović, EPS head of ancillary services, then named the Nikola Tesla A, Kostolac A, Novi Sad and Zrenjanin plants as the most suitable sites, citing their chemical water treatment, district heating connections and strong grid [4]. He also offered an illustrative calculation: replacing fuel oil as backup fuel with hydrogen at Nikola Tesla A would require a 97 MW electrolyser running close to 9,000 hours a year [4].
Notably, the sites named in 2025 and in 2026 do not match. The analysis pointed to sites with water treatment and district heating, while the call highlights Morava and Kolubara A. The call does not explain the difference. One possible reading is that EPS is keeping some sites under consideration for its own needs while offering partners those whose generating future is less certain. That is the editorial team's assessment, not EPS's stated position.
Why the sites are worth more than they appear
The value of the infrastructure on offer should be seen against the backdrop of grid access. An amendment to the decree on the conditions for the delivery and supply of electricity moved the window in which the transmission system operator carries out connection studies for pending requests from July–October 2026 to September–December 2029, a delay of three years [5]. The industry association RES Serbia called this a direct brake on new connections [6].
The rule covers large wind and solar projects, but also end users and storage operators connecting to the system managed by Elektromreža Srbije [5]. For an investor planning an electrolyser on a new site, that means years of uncertainty over the grid connection. In these circumstances, a site with existing public-utility infrastructure has strategic value well beyond the land itself. How far that advantage materialises depends on the terms EPS sets in the second phase, so this too remains an assessment rather than an established fact.
The regulatory framework does not yet exist
The biggest open question is regulatory rather than technical. On 17 March 2026, Minister of Mining and Energy Dubravka Đedović Handanović said that the Energy Development Strategy to 2040 treats hydrogen as an important energy source, and that the coming period would be devoted to building a regulatory framework enabling a hydrogen market [7][8]. In other words, the rules for producing, transporting and selling hydrogen in Serbia have yet to be written.
The government also cited pilot projects under way: one implemented with Germany's KfW development bank, and an EU-supported demonstration facility for hydrogen production and storage at the Vinča Institute [8]. Earlier, the HyDSerbia pilot was carried out with Leipziger Energiegesellschaft, with funding from the German government [9].
The European Union, meanwhile, has completed its own rulebook. Directive (EU) 2024/1788 sets common rules for the transport, supply and storage of hydrogen, and Member States had to transpose it into national law by 5 August 2026 [10]. Serbia is not an EU member, but as a Contracting Party to the Energy Community it takes over parts of EU energy law through that organisation's decisions. The wider the gap between the two frameworks, the harder it will be for projects in Serbia to reach European buyers and financing.
Green hydrogen in a coal-based system
There is one fundamental point every investor needs to understand. Hydrogen made by electrolysis is not green simply because it is made by electrolysis. It is only as clean as the electricity that produces it. Power systems in the Western Balkans still depend heavily on coal [11], so an electrolyser drawing from the grid would produce hydrogen with a high carbon footprint.
For hydrogen destined for the European market, the relevant rules are the EU criteria for renewable fuels of non-biological origin (RFNBO) set out in Delegated Regulation (EU) 2023/1184. They require additionality (supply from new renewable capacity), temporal correlation between electricity and hydrogen production (monthly until the end of 2029, hourly from 2030) and geographic correlation [12]. The same rules apply to hydrogen imported into the EU, demonstrated through recognised certification schemes.
The practical consequence is clear: a green hydrogen project on an EPS site makes sense only if it is linked to dedicated new renewable capacity or to contracts for its output. It is no coincidence that the same call seeks solar and wind plants. Combining the two groups, renewable capacity and electrolysis sites, could prove the most interesting outcome of this procedure, even though the call does not explicitly provide for it.
There is a second reason why the origin of hydrogen matters. Since 1 January 2026, the Carbon Border Adjustment Mechanism (CBAM) has applied in full, and hydrogen is among the covered goods alongside electricity, iron and steel, aluminium, cement and fertilisers [13]. For Serbian exporters, this means the carbon footprint of production is becoming a cost, and low-carbon hydrogen a potential tool for reducing it.
Regional context
EPS is not the first utility in the region to invite the market to offer it projects. Croatia's HEP, Elektroprivreda BiH and Elektroprivreda Republike Srpske have taken similar steps [2]. As early as 2020, for example, Elektroprivreda BiH launched a call to buy operating and development-stage renewable projects, ranking them by levelised cost of generation [14]. For the hydrogen market, the EPS call stands out because it names green hydrogen explicitly and offers the utility's own power plant sites for its development.
Who should pay attention
- Electrolysis project developers, who gain access to sites with existing infrastructure at a time when connecting new sites is uncertain.
- Electrolyser and equipment manufacturers, as an early signal of a possible market in Serbia whose size and pace are still to be defined.
- Renewable energy investors, because pairing dedicated renewable capacity with electrolysis is becoming a condition for hydrogen to count as renewable.
- Industrial exporters exposed to CBAM, for whom domestic low-carbon hydrogen could become part of a decarbonisation strategy.
- Development banks and lenders, for whom a clear partnership model with a public utility will be a precondition for financing.
What to watch
The key question is whether EPS issues detailed documentation for Group 2 or cancels the procedure, and what cooperation model it offers. At the time of writing (27 November 2026), we found no public announcement on the outcome of Group 2. Three further developments are worth watching: whether the Ministry of Mining and Energy publishes a draft regulatory framework for the hydrogen market, how the question of connecting new renewable capacity is resolved, and whether EPS links the two groups of the call into joint renewable-plus-electrolysis projects.
The EPS call does not guarantee that a green hydrogen plant will soon be built in Serbia. It does change the nature of the conversation: the question is no longer whether hydrogen has a place in the Serbian energy system, but on what terms, at which sites and with whom.
Sources
- Elektroprivreda Srbije, "EPS objavio javni poziv za otkup OIE projekata", 8 September 2026. https://www.eps.rs/cir/vesti/Pages/javni-poziv-za-otkup-OIE-projekata.aspx
- Balkan Green Energy News, "Serbia's EPS issues call to acquire renewable energy projects", 7 September 2026. https://balkangreenenergynews.com/serbias-eps-issues-call-to-acquire-renewable-energy-projects/
- Energy News, "Serbia's EPS Launches Public Tender for Renewable Energy Projects", September 2026. https://energynews.pro/en/serbias-eps-launches-public-tender-for-renewable-energy-projects
- Balkan Green Energy News, "Serbia's EPS examining green hydrogen production", 27 March 2025. https://balkangreenenergynews.com/serbias-eps-examining-green-hydrogen-production
- Balkan Green Energy News, "Serbia delays renewables connection procedure until 2029", 27 May 2026. https://balkangreenenergynews.com/serbia-delays-renewables-connection-procedure-until-2029/
- Energy News, statement by RES Serbia on the postponement of connection studies, September 2026. https://energynews.pro/en/serbias-eps-launches-public-tender-for-renewable-energy-projects
- N1, "Energy minister: Serbia aims to be part of Europe's hydrogen transition", 17 March 2026. https://n1info.rs/english/news/energy-minister-serbia-aims-to-be-part-of-europes-hydrogen-transition/
- Government of the Republic of Serbia, "Serbia seeks to be part of European hydrogen transition", 17 March 2026. https://www.srbija.gov.rs/vest/en/272795/serbia-seeks-to-be-part-of-european-hydrogen-transition.php
- Balkan Green Energy News, "Serbia implementing first green hydrogen pilot project with Germany", 1 November 2024. https://balkangreenenergynews.com/?p=75502
- EUR-Lex, summary of Directive (EU) 2024/1788 on common rules for the internal markets for renewable gas, natural gas and hydrogen. https://eur-lex.europa.eu/legal-content/EN/LSU/?uri=oj:L_202401788
- NewPolis, "Belgrade Green Hydrogen Conference: between ambition and practical constraints", 19 March 2026. https://newpolis.media/belgrade-green-hydrogen-conference-between-ambition-and-practical-constraints/
- Commission Delegated Regulation (EU) 2023/1184 on the methodology for renewable fuels of non-biological origin. https://eur-lex.europa.eu/eli/reg_del/2023/1184/oj
- European Commission, "CBAM successfully entered into force on 1 January 2026", 14 January 2026. https://taxation-customs.ec.europa.eu/news/cbam-successfully-entered-force-1-january-2026-2026-01-14_en
- Balkan Green Energy News, "EPBiH is looking for renewable projects to expand its green portfolio", 2 November 2020. https://balkangreenenergynews.com/epbih-is-looking-for-renewable-projects-to-expand-its-green-portfolio/