The EU Agency for the Cooperation of Energy Regulators (ACER) published its annual monitoring report on European hydrogen markets on 13 November 2026 [1]. The figure most often quoted from it is that only around 4.2 GW of electrolysis has been committed in the EU, against the 30 to 58 GW foreseen for 2030 [1]. For Serbia and the Western Balkans, however, a different message matters more: the regulator recommends that the European Commission and Member States "recalibrate" their ambitions through the forthcoming revision of the EU Hydrogen Strategy [1]. In other words, the targets that create demand for renewable hydrogen in the EU may change at precisely the moment the region is starting to build its own plans around them.
The report is not a decision and changes no legislation. ACER is the EU regulatory agency that monitors the market and makes recommendations; targets are set by the European Commission, the Council and the European Parliament. Even so, the report offers the most complete official picture of how much of Europe's hydrogen market has actually been built, and that picture now feeds into a wider policy review that is already under way.
What ACER finds
According to the report, water electrolysis capacity in the EU reached 490 MW by the end of 2025, 5.7 times the 2020 level [1]. That is still only 0.9% of total EU hydrogen production capacity, up from 0.5% a year earlier [1]. Germany (219 MW) and Denmark (100 MW) have the largest installed capacity [1]. For comparison, ACER's previous report, published in December 2025, recorded 308 MW of electrolysis at the end of 2024 [2].
Total EU hydrogen production capacity stood at 10 million tonnes a year in 2025, with unabated natural gas reforming accounting for 89% and by-product hydrogen for a further 10% [1]. Demand in 2025 was 7.3 million tonnes, 3% lower than in 2022 [1]. The market, in other words, is not growing; only the way hydrogen is produced is changing, and slowly.
Of the roughly 4.2 GW of electrolysis that is operational, under construction or has reached final investment decision (FID), about 49%, or 2.1 GW, is destined for refineries [1]. ACER also notes that all 15 of the largest electrolytic projects to reach FID received EU or national support [1]. Without public money, for now, there are no large projects.
The cost gap remains the main barrier. Based on European Hydrogen Bank auction data analysed by ACER, applicants' production costs range from EUR 5.3/kg in Spain to EUR 12.6/kg in Austria, while hydrogen from gas reforming without carbon capture averaged EUR 3.9/kg in 2025 [1]. Applicants' costs exceed that average in every country shown [1].
Public money does not guarantee construction
The part of the report that matters most to investors concerns projects that won support but were not built. ACER states that a third of Innovation Fund hydrogen grant value has been cancelled, that the Hydrogen Bank's second auction lost most of its selected capacity, and that only around a fifth of hydrogen projects under the Important Projects of Common European Interest (IPCEI) had reached FID by 2025 [1].
ACER therefore recommends that EU and national funding be targeted at mature projects [1]. That recommendation bears directly on future applicants from the region. The European Commission plans to open the fourth European Hydrogen Bank auction in December 2026 with a planned budget of up to EUR 500 million [8]. Western Balkan projects are not the target of these auctions, but the maturity criteria the EU now emphasises are likely to become a benchmark for the development banks that finance projects in the region as well. The latter is the editors' assessment.
Rules that even Member States have yet to transpose
Directive (EU) 2024/1788 on common rules for the internal markets for renewable gas, natural gas and hydrogen was due to be transposed into national law by 5 August 2026 [5]. According to ACER, one Member State (Italy) has notified the Commission of full transposition and 11 have transposed it partially [1]. Austria, Belgium, Bulgaria, Lithuania, Portugal, Slovakia and Spain have notified separate measures; the Czech Republic, Germany, Hungary and Poland have transposed certain provisions; and in Denmark, Finland, Latvia, the Netherlands and Slovenia public consultation on draft legislation is ongoing or concluded [1].
This matters to the Western Balkans for a practical reason. Serbia is not an EU member, but as a Contracting Party to the Energy Community it takes over part of the EU's energy legislation. When most EU Member States have missed the deadline for hydrogen market rules, it is hard to expect the region to obtain a fully aligned framework quickly. Serbia's Minister of Mining and Energy, Dubravka Đedović Handanović, said on 17 March 2026 that the Energy Development Strategy to 2040 treats hydrogen as an important energy source and that the coming period would be devoted to building a regulatory framework for a hydrogen market [9]. In our research for this article we found no published draft of that framework.
The report also records the first steps in infrastructure. According to ACER, 622 km of hydrogen pipelines have been commissioned in the EU, another 555 km are under construction in Austria, Belgium, Germany and the Netherlands, and 42,259 km of transmission projects are planned, 24,352 km of them by 2030 [1]. Pilot hydrogen storage facilities in Austria, Germany, France and Hungary have a combined capacity of just 266 tonnes [1].
Same problem, different numbers
ACER's figures are not the only ones. In its Clean Hydrogen Monitor 2026, the industry association Hydrogen Europe reports 677 MW of operational electrolysis in Europe as of July 2026, spread across 253 plants [3]. The difference from ACER's 490 MW most likely reflects different cut-off dates and scope: ACER gives the position at the end of 2025, Hydrogen Europe up to July 2026. Hydrogen Europe expects 1.6 GW to come online during 2026, around a third of it the Swedish Stegra project, while about 3.7 GW is under construction, mostly in Germany (1.3 GW) and Sweden (0.8 GW) [3]. In the first half of 2026, around 0.5 GW reached FID, mainly refinery projects in Spain [3].
Hydrogen Europe is an interested party representing the industry, and its assessments should be read in that light. The association estimates that the shortfall against the 2030 targets in the Renewable Energy Directive (RED III) is about 2.6 million tonnes a year, or 25 to 30 GW of electrolysis, and warns that, according to a leaked draft of a future directive (RED IV), the binding targets for industry and transport could be replaced by an indicative objective [3]. Speaking at European Hydrogen Week in Brussels, the association's chief executive, Jorgo Chatzimarkakis, warned that weakening or revising the targets at this point would only add to uncertainty [4]. Celine Gauer of the European Commission's Directorate-General for Energy told the same event that a 90% emissions reduction by 2040 remains the end point [4].
Why the 42% target matters
RED III, Directive (EU) 2023/2413, requires Member States to ensure that at least 42% of the hydrogen used in industry is a renewable fuel of non-biological origin (RFNBO) by 2030, and at least 60% by 2035 [6]. That obligation creates most of the predictable demand for renewable hydrogen in the EU, including demand for imports. In its policy status table, ACER lists the target as still at the transposition stage [1].
On 26 October 2026 the European Commission launched a consultation on a new hydrogen strategy, being prepared alongside the renewable energy framework to 2040; the deadline for input passed on 23 November [7]. ACER's call to recalibrate ambitions therefore arrives just as the Commission is drafting the new strategy. What the outcome will be is not yet known.
What it means for Serbia and the region
Hydrogen plans in Serbia and the wider region largely rest on the assumption that the EU will create large and stable demand for renewable hydrogen and its derivatives. In September 2026, Elektroprivreda Srbije (EPS) invited partners to jointly develop green hydrogen projects at its thermal power plant sites [10]. Since 1 January 2026, hydrogen has been among the products covered by the Carbon Border Adjustment Mechanism (CBAM) [11], which turns the carbon footprint of hydrogen exported to the EU into a cost.
In the editors' assessment, ACER's report does not overturn that logic, but it complicates it in three ways. First, if the EU softens its binding targets, demand for imported renewable hydrogen could be smaller and less predictable than earlier plans assumed. Second, if public money is steered towards mature projects, early-stage projects in the region will find it harder to secure finance without a clear site, offtaker and grid connection. Third, slow transposition within the EU itself means that regulatory alignment in the Energy Community is unlikely to move faster.
There is another side. The fact that almost half of committed EU electrolysis is being built for refineries shows where demand is most certain: among existing industrial users of grey hydrogen that have an obligation or an incentive to replace it. For the region, this suggests that projects tied to domestic industrial users and to exporters facing CBAM stand on firmer ground than projects based solely on exporting hydrogen. This, too, is the editors' assessment rather than an ACER finding.
Who this matters to
- Electrolysis project developers in the region, because European financiers increasingly look for project maturity, not just capacity on paper.
- Power utilities and gas system operators, which are planning infrastructure around European targets that may change.
- Industrial exporters facing CBAM, for whom domestic low-carbon hydrogen remains a potential decarbonisation tool, regardless of the EU's import targets.
- Ministries and regulators, who are drafting a hydrogen market framework at a time when the European framework is under review.
- Development banks, which are likely to take ACER's findings on cancelled grants into account when assessing risk.
Risks and unknowns
The biggest unknown is the outcome of the strategy review and of any new renewable energy directive. The leaked draft cited by Hydrogen Europe is not an official Commission document, and the final text may keep binding targets. ACER's capacity data also refer to the end of 2025 and so do not capture projects commissioned during 2026. Finally, lower gas prices or a faster fall in electrolyser costs could narrow the cost gap more quickly than the report assumes.
What to watch
In the coming months it is worth following the proposal for a new EU hydrogen strategy and renewable energy framework to 2040, the outcome of the fourth European Hydrogen Bank auction, planned to open in December 2026 [8], and Member States' progress in transposing Directive (EU) 2024/1788. For Serbia, the key question is whether the Ministry of Mining and Energy will publish a draft hydrogen regulatory framework and how it will align it with European rules that are changing at the same time. At the time of writing (27 November 2026) we had not found an ACER press release accompanying this report, so this article relies on the document itself.
ACER does not say that hydrogen has failed. It says that the market is far smaller than plans foresaw and that policy should adjust to reality. For a region that is just starting out, that is a reason to build plans on certain domestic demand rather than on assumptions about a European market that is still taking shape.
Sources
- ACER, ‘European hydrogen markets 2026 Monitoring Report’, 13 November 2026. https://www.acer.europa.eu/sites/default/files/documents/Publications/ACER-2026-Monitoring-Report-European-hydrogen-markets.pdf
- ACER, ‘Hydrogen progress hampered by high costs and slow transposition’, 2 December 2025. https://www.acer.europa.eu/news/hydrogen-progress-hampered-high-costs-and-slow-transposition
- Hydrogen Europe, ‘Clean Hydrogen Monitor 2026’, October 2026. https://hydrogeneurope.eu/wp-content/uploads/2026/10/Clean_Hydrogen_Monitor_09-2026_withoutAnnex.pdf
- Balkan Green Energy News, ‘Hydrogen Europe: Capacity nears 1 GW, charting path to 4 GW by 2030’, 2 November 2026. https://balkangreenenergynews.com/hydrogen-europe-capacity-nears-1-gw-charting-path-to-4-gw-by-2030/
- EUR-Lex, summary of Directive (EU) 2024/1788 on common rules for the internal markets for renewable gas, natural gas and hydrogen. https://eur-lex.europa.eu/legal-content/EN/LSU/?uri=oj:L_202401788
- EUR-Lex, Directive (EU) 2023/2413 (RED III) amending Directive (EU) 2018/2001, 18 October 2023. https://eur-lex.europa.eu/eli/dir/2023/2413/oj
- European Commission, Directorate-General for Energy, ‘Hydrogen Strategy – Commission launches consultation’, 26 October 2026. https://energy.ec.europa.eu/news/hydrogen-strategy-commission-launches-consultation-2026-10-26_en
- European Commission, Directorate-General for Climate Action, ‘IF26 Hydrogen Auction’, accessed 27 November 2026. https://climate.ec.europa.eu/areas-action/eu-funding-climate-action/innovation-fund/calls-proposals/if26-hydrogen-auction_en
- Government of the Republic of Serbia, ‘Serbia seeks to be part of European hydrogen transition’, 17 March 2026. https://www.srbija.gov.rs/vest/en/272795/serbia-seeks-to-be-part-of-european-hydrogen-transition.php
- Elektroprivreda Srbije, ‘EPS objavio javni poziv za otkup OIE projekata’ (EPS publishes public call for acquisition of RES projects), 8 September 2026. https://www.eps.rs/cir/vesti/Pages/javni-poziv-za-otkup-OIE-projekata.aspx
- European Commission, ‘CBAM successfully entered into force on 1 January 2026’, 14 January 2026. https://taxation-customs.ec.europa.eu/news/cbam-successfully-entered-force-1-january-2026-2026-01-14_en